• Construction of ductile pipeline (DCI) with all necessary civil and mechanical works:
-DN200 in length of 740m;
-DN250 in length of 571m;
-DN300 in length of 380m;
-DN400 in length of 1620m;
-DN500 in length of 846m;
-Installation of all required fittings and armatures.
• Construction of pipeline (PEHD PE100 PN10) with all necessary civil and mechanical works:
-Ø63 in length of 160m;
-Ø90 in length of 616m;
-Ø110 in length of 944m;
-Ø160 in length of 8149m;
-Ø180 in length of 231m;
-Ø200 in length of 450m;
-Ø225 in length of 162m;
-Ø250 in length of 120m;
-Ø300 in length of 200m;
-Ø450 in length of 70m;
-Ø560 in length of 260m;
-Installation of all required fittings and armatures.
• Hydro-geological studies on the water spring „Kajnak“:
-Drilling of five boreholes, Ø200mm, depth of 50m, installation of perforated PVC pipes in boreholes, allows installation of new pumps. The result of
testing is a NEW quantity of water of 60 l/s.
Investor: PE „Vodovod i kanalizacija“ Bar, 2007-2009
Total value of project: €4.857.405, 81.