• Construction of the ductile pipeline (DCI) with all necessary civil and mechanical works:
-DN150 in length of 120m;
-DN100 in length of 20m;
-Installation of above-ground hydrants;
-Installation of all required fittings and armatures.
Investor: Municipality of Bar, 2009
Total value of project: €18.000